Execution of works to ensure power supply for biofuel pellet production plant
VOLTAGE performed a scope of design, construction, installation and commissioning works on the power supply of the enterprise:
• construction of 10 kV overhead line;
• construction of Transformer Substation
2x1600 kVA 10 / 0,4 kV;
• installation of busbars 2500 A;
• installation of external and internal power electric networks and electric lighting networks;
• installation of cable networks for low-current systems;
• installation of lightning protection;
• installation of automation networks of technological equipment.
Location of the object: Vinnytsia region Turbines.
Customer: Vin-Peleta LLC (SMART Holding)