5.4 MW Solar Power Plant

Solar Power Plant Design & Construction (Full EPC)

VOLTAGE performed as a General Contractor (EPC Contractor) on the project implementation of 5.5 MWp SPP construction.

VOLTAGE provided the development of design solutions and the following works:

land planning, partial vertical planning and landscaping;
partial movement of earth masses;
supply of good-quality materials and equipment;
installation of an external fence;
construction and installation works;
installation of electrical and other related engineering networks at the project site;
installation of internal electrical networks for delivery of generated power to the grid, as well as for SPP auxiliary power supply;
delivery and installation of package transformer substations (PTS-0,4 / 10 kV);
construction of an administrative and household complex with appropriate infrastructure;
installation of a monitoring system;
commissioning works;
Paperwork for NCRECP (for obtaining a license and establishing a “green” tariff).


Number of installed solar panels: 20456 pcs. of a nominal power 270W.

Number of installed inverters: 46 pcs., type “INGECON SUN 100 TL” of 100 kW.



The construction period lasted 5 months. After completing all construction and installation works and the object commissioning, VOLTAGE provides O&M services for this SPP.



Location of the object: Vinnytsia region, Bershad district, village Velyka Kyriivka

Customer: ELEKTROSOLAR LLC.

Project implementation period: 2018 – 2019